Project news

FPL concreting the last pillar foundations in B&T Quang Binh wind farm cluster project

  • 11.06.2021
  • |
  • 4789 (views)

On the night of June 11, 2021, FECON Pile Construction and Construction Joint Stock Company (FPL) carried out the pouring of the last Turbine pillar foundation of the BT1 & BT2 package at the B&T Quang Binh Wind farm project.


In hot weather conditions of 40 degrees Celsius, by 17h00, the steel acceptance test has been completed. FPL engineers and workers rushed to prepare machinery and materials to complete the 28th pillar at 20:00.

The project contract "B&T Quang Binh wind farm cluster" was signed on July 20, 2020 between FPL and BT Wind Power Joint Stock Company with a total value of more than 200 billion VND. The project has a total investment of nearly 7,000 billion VND, invested by B&T Wind Power Joint Stock Company, located in Hai Ninh commune, Quang Ninh district, Quang Binh province. B&T Wind farm cluster is the largest wind farm on land with capacity in Vietnam up to now. FPL is honored to be the largest construction company, taking on 50% of the work volume at the project.

More specifically, in this project, FPL performs the following tasks:
1. Construction of 15km of roads, accounting for 30% of traffic system volume at the project.
2. Producing and supplying 60,000m3 of concrete of all kinds, accounting for 100% of the total concrete volume of the whole project.
3.Construction of 50% of the PHC pile and bored pile of the project
4. Directly construct 29 out of 50 foundation pillars of the project.

This is a key project of the Parent Company and also the most important project of FPL in 2021. With this project, FPL affirms the capacity, brand and commitment of FPL to the Group.

Related news

Comments

Your email address will not be published. Required fields are marked *