The Ba Na Hills project has been implemented since the last days of 2022. As of March 3, 2023, FPL has constructed 87 piles at the Voco Hotel building. Next, the Project Management Board plans to carry out drilling construction at the Podium P1A and P1C areas, and the grounds of the Arena and Indoor garden areas are being leveled.
The project continues to encounter constant difficulties due to specific terrain conditions at an altitude of 1450m above sea level, construction during the rainy season, so it often encounters prolonged rain, thick fog, poor visibility and close to the edge of the cliff. The daily life of engineers and workers also faces many difficulties due to frequent power and water outages, making transportation difficult.
However, everyone at the Project still strives every day to bring the project to a smooth finish line. Engineers often encourage each other, "Do your best, the rainy season is almost over...!". Hopefully sunny days will quickly come to Ba Na Hills construction site so that the project can smoothly accelerate in the next phase.
Comments