FPL implemented construction of FPT Hau Giang project

  • 24.01.2024
  • |
  • 2105 (views)

In early 2024, FPL Company excitedly received the news of winning the bid for the pile pressing project of Inter-school High School (FPT Hau Giang) with FPT Education as the Investor. In this project, FPL undertook drilling construction and provided 244 D-600 piles with a total contract value of more than 10 billion VND.

The FPT Hau Giang Inter-Level High School project has a total usable area of ​​more than 05 hectares with 02 lecture hall buildings, 02 service buildings, sports practice and competition hall, outdoor sports area, football field, outdoor landscape and auxiliary works. When put into use, the school will have the capacity to receive about 5,100 students/school year and create jobs for about 300 teachers, administrators and staff.

After the process of preparing and assembling machinery, the Project Management Board started the project on January 17, 2024, with a construction schedule of 75 days, including holidays and Tet.

Although the time took place close to the days leading up to Tet, making it very difficult to mobilize equipment and personnel, the Project Management Board 's engineers still rushed to complete and handed over on schedule as committed. Thereby, FECON FPL affirmed position as TOP reputable contractor in the field of construction and pile supply in the market.