On October 1st, 2020, FECON Piling and Construction Joint Stock Company (FPL) and ZYX Vietnam Construction Co., Ltd signed a contract to construct the item "construction of borred piles and pipe piles" of "Bac Ninh high-tech power generation waste incineration plant project” has a total contract value of VND 25,2 billion with a schedule of 97 days.
The project is located in Thanh Ha village, An Thinh commune, Luong Tai district, Bac Ninh province, the project scale is to build a system of waste incineration plants to generate electricity with a waste treatment capacity of 300 tons/day.
Once put into operation, it will contribute to thoroughly solving the problem of daily-life waste and other solid wastes generated daily and remaining in the whole province of Bac Ninh, contributing to building a green environment. clean. Not only that, with the technology of incineration and recovery of calorific value for electricity generation, the plant will also contribute to providing 33.6 million KWh of electricity annually to the national grid.
Within 97 days of project construction, FPL faced numerous difficulties such as: having to stop construction due to the strong outbreak of Covid 19, adverse weather, fresh water supply for mixing ben was not available due to Luong District. The special talent of salt water source....However, with the inherent rich experience in the field of pile construction, the high determination of the Board of Directors, the solid rear is the best support from the offices/offices, unanimously agree for the common goal of safe construction, on schedule.
Exceeded expectations, within 75 days the project was completed ahead of schedule, safely, highly appreciated by the investor, contributing to building the image of a clean, beautiful, zero-waste countryside in general and the development of sustainable development. sustainable development of Luong Tai district, Bac Ninh province in particular.